Major Construction Updates 

ARC-Banner Haldimand East Elementary.jpg

The following major contruction updates are decisions of the
Haldimand 



Anna Melick Memorial School is hosting an Open House to celebrate the school's history. 

Celebrate its history on Saturday, April 29, 2017 from 11:00 a.m. - 2:00 p.m. at the school. An invitation is being extended to all students, parents, staff (both past and present) and community members to join us in celebrating our 58 years in education.
Anna Melick Logo.jpg
Fairview Avenue Redevelopment 
Grand Erie District School Board held a public meeting on Thursday, April 13, 2017 to share information with the public about the new school build. 

The information session was led by Salter Pilon Architects and Grand Erie District School Board staff to shared the school design and learn more about the project.
Scope:
Construction of a new elementary school to accommodate the consolidation of Fairview Avenue PS and Grandview Central PS on the existing Fairview Avenue PS site. The new construction will include child care room and child and family program spaces. The current school will be demolished following occupancy of the new elementary school.

Timeline:

  • Schematic Design and Stakeholder consultation: Schematic Design Complete | Open House April 13, 2017
  • Site Plan Review and Agreement: Mid-April to Mid-July 2017 
  • General Contractor Tender Posting: June 1 2017 (Three weeks)
  • General Contractor Tender Award: Week of June 26, 2017
  • Break Ground / Commence Construction Phase: Week of July 3, 2017 
  • Occupancy: August 2018



Rendering SW.jpg


























Thompson Creek Addition

Scope: 
Create four new classrooms to facilitate the consolidation of Anna Melick Memorial School students with Thompson Creek effective September 1, 2017.

Timeline: 
  • February 2017 - Complete design phase and seek approval to issue tender. 
  • March 2017 - Seek Board approval to award contract work.
  • April to August 2017 - Complete project work.
  • September 2017 - New space occupied by staff and students.
Status:
Design complete, tender issued and reviewed. Pending Board Approval, the contract will be awarded and construction will commence in April.

Budget:
Capital Priorities Grant approval has been received from the Ministry of Education for this project. ​


Thompson Creek Logo.jpg















 
 
 