The following major construction updates are decisions of the Haldimand East Elementary Accommodation Review.
Fairview Avenue Redevelopment
Grand Erie District School Board held a public meeting on Thursday, April 13, 2017, to share information with the public about the new school build.
The information session was led by Salter Pilon Architects and Grand Erie District School Board staff to share the school's design and more about the project.
Scope:
Construction of a new elementary school to accommodate the consolidation of Fairview Avenue PS and Grandview Central PS on the existing Fairview Avenue PS site. The new construction will include child care room and child and family program spaces. The current school will be demolished following occupancy of the new elementary school.
Timeline:
Scope:
Create four new classrooms to facilitate the consolidation of Anna Melick Memorial School students with Thompson Creek, effective September 1, 2017.
Timeline:
Status:
Design complete, tender issued and reviewed. Pending Board Approval, the contract will be awarded and construction will commence in April.
Budget:
Capital Priorities Grant approval has been received from the Ministry of Education for this project.